Department Action Items & Compliance Tracking
Closed ATRs require documentary evidence and Member Secretary verification. Zero unresolved tasks close without proof.
16 Actions Overdue (district)4 Delayed in this register
RSC-PLG-01/M07/A3/01District Road Safety Committee, Palghar (Mtg #7)In Progress
Install W-beam crash barriers on Manor-Wada road ghat section (2.4 km stretch)
Lead: Public Works Department (PWD)·Target: 30 Nov 2026·Progress: 85%
Latest ATR (05 Nov 2026): Fabrication of metal beam crash barriers completed. 2.0 km installed on site along curve chainages. Remaining 400m ongoing and targeted by 25 Nov.[Pending Verification]
RSC-PLG-01/M06/A3/02District Road Safety Committee, Palghar (Mtg #6)Delayed (124 days overdue)
Rumble strips, solar blinkers and cautionary signage at Charoti black spot junction on NH-48
Lead: Public Works Department (PWD)·Target: 15 Jul 2026·Progress: 40%
Latest ATR (20 Aug 2026): Thermoplastic paint procurement delayed due to coastal monsoon rains. Tender reinvited under Special Road Safety grant.[Clarification Requested]
DDMA-PLG/M11/A2/01District Disaster Management Authority, Palghar (Mtg #11)Delayed (149 days overdue)
Desilting of critical nallas & creeks in 3 coastal villages (Dahanu & Palghar) before next monsoon
Lead: Irrigation & Water Resources·Target: 20 Jun 2026·Progress: 30%
Latest ATR (15 Jun 2026): Initial desilting undertaken at 1 village; machinery breakdown halted remaining stretches.[Clarification Requested]
DHS-PLG/M09/A4/03District Health Society, Palghar (Mtg #9)Delayed (103 days overdue)
Filling of vacant Medical Officer (Class-I) posts at 4 remote tribal Primary Health Centres in Jawhar & Mokhada
Lead: Public Health Department·Target: 05 Aug 2026·Progress: 50%
Latest ATR (28 Sep 2026): 2 bond-service doctors appointed. Requisition sent to Commissionerate of Health for remaining 2 specialist posts.[Pending Verification]
DLBC-PLG/M14/A5/01District Level Banking Committee, Palghar (Mtg #14)Delayed (67 days overdue)
Clearance of 420 pending tribal horticulture & chikoo crop loan applications at two regional bank branches
Lead: Lead Bank & Planning Department·Target: 10 Sep 2026·Progress: 65%
Latest ATR (20 Oct 2026): 275 crop loans disbursed. Remaining 145 pending verification of digitised 7/12 land extracts.[Pending Verification]